甲骨文就新墨西哥州Stargate数据中心发出不可抗力通知
原标题:Oracle sends force majeure notice on its New Mexico Stargate data center
AI 摘要
甲骨文就其位于新墨西哥州的Stargate数据中心园区Project Jupiter向开发商Blue Owl Capital发出不可抗力通知。该通知并非意在退出主要租户身份,而是允许甲骨文在设施未能按2028年上线目标交付时延迟付款。此举背景是该园区因能源供应问题屡遭挫折,包括Bloom Energy燃料电池所需天然气管道因监管拒绝而延期近六个月,以及空气质量许可仍待审批。
正文节选
Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thursday. Force majeure clauses, common in energy and commodities contracts, excuse a party from contractual obligations when events outside its control get in the way. Oracle is not seeking to exit as the campus’s main tenant, according to Bloomberg’s sources. Instead, the notice would allow the company to delay payments should the facility miss its 2